Court of Appeals for the D.C. Circuit

Northwest Airlines, Inc. v. Federal Aviation Administration, Memphis-Shelby County Airport Authority, Intervenor

14 F.3d 64 · 1994 U.S. App. LEXIS 1731 · 304 U.S. App. D.C. 302

February 4, 1994 · Docket 92-1245

Queued for AI processing — next in lineest. ~144 min

Headnotes

Generated summaries
  1. Headnote 1

    The D.C. Circuit reviewed the FAA’s construction of the passenger‑facility‑charge statute under the two‑step Chevron framework, determining the statute was silent on the precise question and the agency’s reading was reasonable.

  2. Headnote 2

    Northwest alleged the FAA’s approval of the Memphis PFC was arbitrary because the agency failed to weigh the airline’s economic and competitive concerns.

  3. Headnote 3

    Northwest did not raise its frequent‑flyer objection in the FAA’s administrative proceeding, so the court dismissed that claim for lack of exhaustion.

  4. Headnote 4

    The statute’s consultation mandate applies to all projects presented in a PFC application; failure to consult renders the agency’s approval of that project invalid.

  5. Headnote 5

    The court held that the statutory command to finance “specific…eligible airport‑related projects” does not prohibit a two‑step approval process where the charge is imposed first and the project(s) are chosen later.

  6. Headnote 6

    These regulatory safeguards support the FAA’s two‑step “alternative‑use” policy by requiring both an initial description of eligible alternatives and a later approval of the specific project before expenditure.

  7. Headnote 7

    The court interpreted the three statutory criteria for PFC approval—capacity, noise reduction, competition—so that meeting any single criterion fulfills the statutory requirement.

  8. Headnote 8

    The court held that Section 102’s factors have no direct bearing on the FAA’s PFC‑approval decisions, which are governed solely by the PFC statute.

  9. Headnote 9

    The agency satisfied its duty by confirming that each proposed project met at least one of the three statutory criteria; the agency’s decision not to assess Northwest’s economic burden was discretionary, not unlawful.

  10. Headnote 10

    The court concluded that the FAA’s authorization of the alternative project was unlawful, but the approval of the primary runway and taxiway projects, which were properly consulted, remained valid.

  11. Headnote 11

    Northwest’s frequent‑flyer challenge was dismissed because the airline’s letters were sent to the wrong FAA office and did not constitute a proper “urge” under 49 U.S.C. app. § 1486(e).

  12. Headnote 12

    The court found the policy reasonable and consistent with the purpose of the PFC statute, concluding that the agency’s interpretation warranted deferential review.

  13. Headnote 13

    The D.C. Circuit evaluated Northwest's challenges to the FAA's interpretation of the passenger‑facility‑charge statute using the Chevron deference analysis.

  14. Headnote 14

    Northwest argued the FAA’s approval of the Memphis PFC was arbitrary and capricious; the court cited the APA standard governing judicial review of agency actions.

  15. Headnote 15

    The court dismissed Northwest’s frequent‑flyer claim because the airline had not raised the issue in the FAA’s administrative proceeding, invoking the exhaustion requirement.

  16. Headnote 16

    Regulations permit airports to seek authority to impose a PFC in advance of identifying a particular use, as long as alternative eligible uses are described and later approved before funds are spent.

  17. Headnote 17

    The statute’s consultation mandate applies to all projects presented as the basis for a PFC application and must be satisfied before the application is submitted.

  18. Headnote 18

    Northwest’s claim that the FAA must weigh its economic and competitive impact was rejected; the agency’s duty is satisfied by confirming eligibility under the statutory criteria.

  19. Headnote 19

    The court held that the public‑interest criteria established for the Civil Aeronautics Board are not directly applicable to the PFC program administered by the FAA.

  20. Headnote 20

    The regulatory scheme provides double checks—description of alternatives at the imprint stage and a second approval before actual expenditure—to satisfy statutory eligibility requirements.

  21. Headnote 21

    The D.C. Circuit evaluated Northwest’s challenges under the Chevron two‑step framework, first looking for a clear congressional command and then deferring to the FAA’s construction of the PFC statute as reasonable.

  22. Headnote 22

    The court dismissed Northwest’s frequent‑flyer claim because the airline never raised the issue in the FAA’s administrative proceeding, invoking the exhaustion requirement of the FAA’s judicial‑review provision.

  23. Headnote 23

    The statute requires prior consultation with airlines, including written descriptions of the projects; the court held that Memphis’s failure to consult Northwest about its backup noise‑compatibility project violated this mandate.

  24. Headnote 24

    Statutory silence on when a specific project must be identified permits the agency, under its regulations, to approve a two‑step process—first imposing the charge, then later approving the particular eligible project(s).

  25. Headnote 25

    Northwest’s argument that the FAA should consider its competitive disadvantage was rejected; the agency deemed such analysis discretionary and not mandated by the PFC statute.

  26. Headnote 26

    The court explained that Section 102’s factors, originally intended for the Civil Aeronautics Board, have no direct bearing on the PFC program, and any limited effect must be read through the Airport and Airways Improvement Act, which the court found insufficient to impose a competition analysis.

  27. Headnote 27

    Regulations 14 C.F.R. §§ 158.25(a) and (b)(14)(ii) compel airports to describe eligible alternatives, and § 158.25(c)(2) obliges a later use‑approval step, ensuring that only eligible projects receive the revenue.

  28. Headnote 28

    Northwest’s argument that the FAA improperly charged frequent‑flyer passengers was not decided because the airline failed to raise the issue in the FAA proceeding, violating the exhaustion requirement of § 1486(e).

  29. Headnote 29

    The court emphasized that the FAA’s judicial‑review provision requires timely objections, citing prior cases that interpreted the statute strictly.

  30. Headnote 30

    The court applied Reiter and Unification Church precedent to read the PFC statute’s “or” as giving the agency discretion to approve projects that meet any single statutory goal.

  31. Headnote 31

    The D.C. Circuit applied the two‑step Chevron framework to FAA’s construction of the passenger‑facility charge statute, finding the statute silent on whether a specific project must be identified before imposing a charge, and thus deemed the agency’s interpretation entitled to deference.

  32. Headnote 32

    Northwest argued the FAA’s approval of the Memphis PFC was arbitrary and capricious because the agency failed to consider economic and competitive effects; the court noted the standard that governs judicial review of agency actions.

  33. Headnote 33

    The court dismissed Northwest’s frequent‑flyer claim because the airline did not raise the issue in the FAA’s administrative proceeding, invoking the exhaustion requirement of the FAA’s judicial‑review provision.

  34. Headnote 34

    Section 1513(e)(11)(C) requires pre‑submission consultation; Memphis failed to consult airlines about its backup noise‑compatibility project prior to the application, violating the statutory mandate.

  35. Headnote 35

    The phrase “specific…eligible airport‑related projects” in §1513(e)(2) links the authority to levy a passenger‑facility charge with the use of the revenue for identified eligible projects.

  36. Headnote 36

    14 C.F.R. §§158.25(a) and 158.25(b)(14)(ii) require a description of alternative uses; the agency then reviews the specific project before any expenditure, ensuring funds are used only for eligible projects.

  37. Headnote 37

    The court relied on Reiter and Unification Church to interpret the three PFC criteria—capacity, noise reduction, competition—as a list where meeting any single element is sufficient.

  38. Headnote 38

    The FAA concluded that it need not evaluate Northwest’s economic burden because the PFC statute only required meeting one of the three listed criteria, and the statute did not compel broader impact analysis.

  39. Headnote 39

    Section 102’s goals were tied to former CAB functions; since the PFC program originated later, the FAA’s duties are limited to the specific criteria in the PFC statute, not the broader public‑interest factors.

  40. Headnote 40

    Northwest’s argument that the agency must weigh its competitive disadvantage was rejected; the FAA’s duty is satisfied by confirming that the project meets at least one statutory criterion, and any further economic analysis is optional.

  41. Headnote 41

    Finding no explicit congressional command on timing, the court applied the second Chevron step and held the agency’s policy reasonable and consistent with the statute’s purpose, granting the process deference.

  42. Headnote 42

    Memphis did not consult Northwest about its noise‑compatibility backup project prior to the application; the court held that portion of the FAA’s approval violated the consultation provision and barred use of PFC funds for that project.

  43. Headnote 43

    The court dismissed Northwest's frequent‑flyer claim because the airline had not exhausted the statutory administrative remedies before seeking judicial relief.

  44. Headnote 44

    Northwest alleged that the FAA’s approval of the Memphis PFC was arbitrary and capricious, invoking the APA standard of review.

  45. Headnote 45

    The D.C. Circuit evaluated the FAA’s construction of the PFC statute using the two‑step Chevron framework.

  46. Headnote 46

    Section 1513(e)(11)(C) requires pre‑application consultation; the FAA’s approval of Memphis’s backup project violated this requirement because the airline was not consulted beforehand.

  47. Headnote 47

    14 C.F.R. §§ 158.25(a) and (b)(14)(ii) allow a two‑step process; the court held this regulatory scheme reasonable and consistent with statutory purpose.

  48. Headnote 48

    The agency concluded that considering Northwest’s potential economic loss was discretionary, not mandatory, when approving the $3.00 Memphis PFC.

  49. Headnote 49

    The court held that the FAA’s PFC decisions are not governed by the public‑interest criteria that applied to former CAB functions.

  50. Headnote 50

    The court found the FAA’s interpretation reasonable given the statutory silence, thus deferring to the agency.

  51. Headnote 51

    Memphis did not consult Northwest on its noise‑compatibility backup project before the application; the court held that portion of the FAA’s approval unlawful.

  52. Headnote 52

    The FAA’s reliance on a later consultation mechanism conflicted with the plain language of §1513(e)(11)(C), which mandates pre‑application notice.

  53. Headnote 53

    The court first asks whether Congress directly addressed the issue; finding the statute silent, it proceeds to step two and defers to the FAA’s reasonable interpretation. (Sentences 105‑114)

  54. Headnote 54

    Northwest alleged the FAA’s approval was arbitrary and capricious; the court cited 5 U.S.C. § 706(2)(A) as the governing standard. (Sentences 31‑33)

  55. Headnote 55

    The court dismissed Northwest’s frequent‑flyer claim because the airline failed to raise the issue in the FAA proceeding, invoking the exhaustion requirement. (Sentences 41‑44)

  56. Headnote 56

    Memphis failed to consult Northwest about its backup noise‑compatibility project before submitting the PFC application, violating the statutory consultation mandate. (Sentences 292‑306)

  57. Headnote 57

    The court upheld the FAA’s two‑step “alternative‑use” policy as a reasonable construction of the silent statutory language. (Sentences 240‑267, 274‑283)

  58. Headnote 58

    The agency held that the statute’s disjunctive “or” language limits its duty to the three goals of capacity, safety, noise reduction, or competition, making broader economic analysis discretionary. (Sentences 121‑132, 138‑146, 156‑162, 180‑182)

  59. Headnote 59

    The court rejected Northwest’s argument that the FAA must apply those general criteria, noting the PFC program’s distinct statutory framework. (Sentences 197‑228)

  60. Headnote 60

    The FAA’s reliance on a later consultation before seeking use‑approval conflicted with the plain language that requires notice “before submission” of the application. (Sentences 300‑306)

  61. Headnote 61

    Northwest’s letters were sent to the wrong FAA office and did not constitute a timely objection, so the frequent‑flyer claim is barred. (Sentences 317‑345)

Opinion

Opinion for the Court filed by Circuit Judge SENTELLE.

Concurring opinion filed by Circuit Judge STEPHEN F. WILLIAMS.

SENTELLE, Circuit Judge:

Petitioner, Northwest Airlines, Inc. (“Northwest”), seeks review of a decision of the Federal Aviation Administration (“FAA”) approving Memphis-Shelby County Airport Authority’s application to impose a $3.00 Passenger Facility Charge (“PFC”) on passengers enplaned at Memphis International Airport. Northwest argues the FAA’s failure to consider the economic and competitive effects of its decision rendered its ruling arbitrary and capricious. See 5 U.S.C. § 706(2)(a) (1988). Northwest also claims that the FAA’s approval of the PFC based on Memphis’s proposed alternative project violated the PFC statute’s requirements that PFC applications be tied to “specific projects,” 49 U.S.C. app. § 1513(e)(2) (Supp. II 1990), and that the airlines be consulted about each of these projects before the application is submitted, id. § 1513(e)(ll)(C). Finally, Northwest argues that the FAA violated the statute by allowing Memphis to impose PFCs on frequent flyer customers.

We do not reach Northwest’s frequent flyer argument because the airline failed to exhaust its administrative remedies as required by 49 U.S.C. app. § 1486(e) (1988). On the merits of Northwest’s remaining challenges, we defer to the FAA’s reasonable construction of the PFC statute and reject the petition for review in large part. However, because we find that the FAA did violate the consultation provisions of the statute with respect to Memphis’s proposed alternative project, we conclude that Memphis may not expend its PFC funds to finance this alternative project.

I. BACKGROUND

In 1990, Congress amended the Federal Aviation Act to allow local public airport authorities to petition the FAA for permission to impose PFCs on passengers using the airport. See Pub.L. No. 101-508, § 9110,104 Stat. 1388-357 (codified as amended at 49 U.S.C. app. § 1513(e) (Supp. II 1990)). The statute authorizes the FAA1 to “grant a public agency which controls a commercial service airport authority to impose a fee of $1.00, $2.00, or $3.00 for each paying passenger of an air carrier enplaned at such airport to finance eligible airport-related projects to be carried out in connection with such airport or any other airport which such agency controls.” 49 U.S.C. app. § 1513(e)(1). The FAA may only authorize an airport to collect PFCs in order to finance

specific ... eligible airport-related' projects] which will—
(i)preserve or enhance capacity, safety, or security of the national air transportation system,
(ii) reduce noise resulting from an airport which is, part of such system, or
(iii) furnish opportunities for enhanced competition between or among air carriers.

Id. § 1513(e)(2)(B).

The statute further provides that “[b]efore submission of an application under [the PFC statute], a public agency shall provide reasonable notice to, and an opportunity for consultation with, air carriers operating at the airport.” Id. § 1513(e)(ll)(C). As part of this consultation process, the airport authority must provide air carriers with written notice of “individual projects being considered for funding through imposition” of PFCs. Id. § 1513(e)(ll)(C)(i)(I).

On January 28, 1992, the Memphis-Shelby County Airport Authority (“Memphis”) requested FAA permission to impose a $3.00 PFC on all passengers enplaned at Memphis International Airport. Memphis’s application identified four primary projects that it hoped to finance with PFC revenue: 1) the acquisition-of land and the relocation of roadways and utilities to allow future airport development; 2) construction of a new runway; 3) reconstruction and extension of an existing runway; and 4) construction of a new taxiway. In addition, Memphis’s application identified a backup project for which the PFC revenue would be used in the event that the FAA failed to approve one or more of its primary projects. This alternative proposal was to use PFC revenues to purchase homes in high noise corridors to reduce the impact of noise on communities surrounding the airport. Memphis had not mentioned this alternative “noise compatibility project” when it consulted with Northwest and other airlines prior to submitting its PFC application.

Ón May 28, the FAA authorized Memphis to impose a $3.00 PFC and approved its runway and taxiway projects. Record of Decision, Memphis-Shelby Comity Airport Authority at 2-3 (May 28, 1992). However, because Memphis had yet to secure the required environmental clearance to proceed with its runway and taxiway projects, see 14 C.F.R. § 158.25(c)(l)(ii)(B), the FAA also approved the noise compatibility project as an “alternative use” for the PFC revenues “in the event that one or more of the primary projects [was] not implemented in a timely manner.” Record of Decision at 4. Thus, the FAA’s decision authorized Memphis only to “impose” the PFC but did not yet grant Memphis approval to “use” the PFC revenue on any particular project. Id.

Northwest now challenges the FAA’s approval of the Memphis PFC.

II. DISCUSSION

A. Standard of Review

Each of Northwest’s objections to the FAA’s approval of the Memphis PFC ultimately attacks the FAA’s interpretation of the PFC statute. We therefore evaluate these challenges under the framework set forth in Chevron U.S.A., Inc. v. Natural Resources Defense Council, Inc., 467 U.S. 837, 842-44, 104 S.Ct. 2778, 2781, 81 L.Ed.2d 694 (1984). Chevron requires us first to ask

whether Congress has directly spoken to the precise question at issue. If we can come to the unmistakable conclusion that Congress had an intention on the precise question at issue our inquiry ends there.... However, if the statute before us is silent or ambiguous with respect to the specific issue[ ] before us, we proceed to the second step. At this stage, we defer to the agency’s interpretation of the statute if it is reasonable and consistent with the statute’s purpose.

Nuclear Info. Resource Serv. v. Nuclear Regulatory Comm’n, 969 F.2d 1169, 1173 (D.C.Cir.1992) (en banc) (citations and internal quotations omitted). We evaluate Northwest’s statutory challenges using this two-step analysis.

B. FAA’s Failure to Consider the Economic and Competitive Effects of its Decision

In comments to the agency, Northwest objected that the imposition of a $3.00 PFC at its Memphis hub would place the airline at a competitive disadvantage with carriers whose hubs did not impose PFCs. Northwest argued that extreme competition in the airline industry would force Northwest to absorb the PFC itself rather than passing the charge along to its passengers. In hopes of escaping this “economic burden,” Northwest urged the FAA to disapprove the Memphis PFC entirely, to lower the amount of the PFC to $1.00, or to exempt connecting passengers from the PFC charge. However, the agency did not weigh Northwest’s potential economic losses as one of the factors bearing on its decision to approve the $3.00 Memphis PFC. Athough the FAA’s final order noted that the PFC, “as authorized by law, is expected to be paid by the passenger,” the agency determined that “[a]ny decision by an air carrier to adjust its ticket prices to absorb the PFC is beyond the scope” of the PFC statute and the agency’s responsibility. Record of Decision at 7. Thus, the FAA did not believe itself bound to consider the potential economic burden on Northwest as one of the factors relevant to its approval of the Memphis PFC.

Northwest now argues that the criteria for PFC approval set forth in the PFC statute, along with the' general “public interest” criteria set forth in the Federal Aviation Act, made economic and competitive considerations “relevant factors” that the FAA was required to consider before approving a PFC at Memphis. Citing Citizens to Preserve Overton Park v. Volpe, 401 U.S. 402, 416, 91 S.Ct. 814, 823, 28 L.Ed.2d 136 (1971), Northwest urges that the FAA’s failure to consider these factors requires that the agency’s decision be set aside. We disagree.

The PFC statute directs the FAA to approve PFCs only for eligible airport-related projects which will— 49 U.S.C. app. § 1513(e)(2)(B) (emphasis added). Northwest argues that this language expressly directed the agency to consider the economic and competitive detriment Northwest would suffer as a result of the FAA’s decision. According to Northwest, competition in the airline industry would force the airline to absorb any PFC imposed at Memphis, rather than passing the fee along to its customers. But, the argument continues, the cost of internalizing this fee would likely cause Northwest to decrease the number of flights it offers through Memphis, thereby diminishing the capacity and competitiveness of the national air transportation system. Because this result would directly contravene two goals of the PFC statute, Northwest argues that the FAA was required at least to consider this potential outcome in deciding to approve Memphis’s request for a PFC.

(i) preserve or enhance capacity, safety, or security of the national air transportation system,
(ii) reduce noise resulting from an airport which is part of such system, or
(iii) furnish opportunities for enhanced competition between or among air carriers.

The FAA denies that the PFC statute requires it to consider whether every PFC-funded project will enhance the capacity and competitiveness of the airline industry. Rather, as the FAA reads the statute, Congress’s use of the disjunctive “or” to join the three PFC criteria means that the agency may approve any “eligible airport-related project” that meets any one of the three statutory criteria.. In this case, the FAA determined that Memphis’s proposed runway and taxiway projects would enhance the capacity and safety of the Memphis airport and that the alternative noise compatibility project would further the statutory goal of reducing airport noise., Having ensured that each possible use of the PFC funds satisfied, one of the statutory goals, the agency claims that it was required to look no further. We defer to the FAA’s interpretation of the statute.

As with all cases of statutory interpretation, “our starting point must be the language employed by Congress.” Reiter v. Sonotone Corp., 442 U.S. 330, 337, 99 S.Ct. 2326, 2330, 60 L.Ed.2d 931 (1979). In this case, Congress chose to join the three criteria for PFC approval with the word “or,” which is “ ‘[njormally ... to be accepted for its disjunctive connotation.’Unification Church v. INS, 762 F.2d 1077, 1084 (D.C.Cir.1985) (quoting United States v. Moore, 613 F.2d 1029, 1040 (D.C.Cir.1979)). Thus, the most natural reading of the statute is the one proposed by the FAA — that is, by joining the criteria for PFC approval with an “or,” Congress wanted only to ensure that all PFC-approved projects furthered one of the three statutory goals.

We acknowledge that it might be possible to read the statute as Northwest suggests — requiring that the agency consider each of the. criteria set forth in § 1513(e)(2)(B) and approve only those projects that make some reasonable accommodation of the three competing factors. See Holyoke Water Power Co. v. FERC, 799 F.2d 755, 761 (D.C.Cir.1986) (MacKinnon, J., dissenting) (noting that the word “or” may sometimes be read to mean “and”). However, “[a]s we must defer to an agency’s reasonable interpretation of an ambiguous statute that it must administer, we need not pass on whether there are valid alternative readings” of the PFC statute. International Union, UMW v. Federal Mine Safety and Health Admin., 920 F.2d 960, 963 (D.C.Cir.1990) (internal citation omitted). Rather, we need only ask whether the FAA’s interpretation is reasonable; and we find it eminently reasonable for the agency to adopt the most natural reading of the statute. We therefore conclude that nothing in the PFC statute compelled the FAA to consider the potential economic harm Northwest might suffer as a result of the agency’s decision to approve a PFC for Memphis.2

Northwest next argues that general provisions of the Federal Aviation Act required the FAA to consider the competitive and economic consequences of its decision. Northwest cites two provisions in support of this argument. It first points to section 102 of the Act, which requires the FAA generally to consider economic and competitive factors when making decisions “in the-public interest.” 49 U.S.C. app. § 1302(a) (1988). Northwest also relies upon section 502(a)(5) of the Airport and Airways Improvement Act, which requires that “all airport and airway programs” be administered in accord with section 102 and “with due regard for the goals expressed therein [such as] fostering competition.” 49 U.S.C. app. § 2201(a)(5) (Supp. II 1990). These general provisions add to the list of “relevant factors” in the PFC statute. According to Northwest, these provisions required the FAA to consider the potential economic and competitive burden its decision would place on Northwest and the airline industry.

We do not agree that the general language of these sections required the FAA to evaluate either the possibility that its decision would harm Northwest financially or the more remote chance that its decision would lead to a decline in airline competition. We begin by noting that the “public interest factors” set forth in § 102 of the Federal Aviation Act, 49 U.S.C. app. § 1302(a), do not apply of their own force to the FAA’s administration of the PFC statute. Section 102 lists factors that the Civil Aeronautics Board (“CAB”) was to consider when regulating for the “public convenience.” Because the CAB’s remaining regulatory functions were transferred to the Department of Transportation, 49 U.S.C. app. § 1551(b)(1)(E), and derivatively to the FAA, 49 C.F.R. § 1.47 (1992), after the CAB’s abolition in 1985 the § 102 criteria bind the FAA when performing former CAB functions. But the PFC program, which was not established until 1990, was never administered by the CAB. Thus, § 102 has no direct bearing on the PFC program.

If the general criteria of § 102 have any bearing on the PFC program at all, it can only be through the provision of the Airport and Airways Improvement Act which requires that “all airport and airway programs ... be administered in a manner consistent with the provisions of section[ ] 102.” 49 U.S.C. app. § 2201(a)(5). Nonetheless, we cannot conclude that a general congressional directive to give “due regard” to goals such as “fostering competition,” id., required the FAA to factor into its PFC approval calculations the possibility that Northwest would make an independent business decision to internalize the cost of the PFC rather than passing it on to its customers, thereby causing the airline possibly to decrease the number of flights' it offers through Memphis, thereby having some effect on competition in the airline industry.

In Horizon Air Industries v. DOT, 850 F.2d 775 (D.C.Cir.1988), we held that § 102 did not require the FAA expressly to consider the effect on competition that would result from its decision to award an exclusive commuter airline route to a particular carrier. Rather, we held that § 102 “merely stated as a general goal ‘maximum reliance on competitive market forces,’ 49 U.S.C. app. § 1302(a)(4); [and that] this generalization can hardly be read as a clear directive to focus' on competitive effects in inherently non-market-oriented proceedings for award of international routes.” Id. at 779. While the PFC approval process may not share the “inherently non-market-oriented” ' nature of the route allocations considered in Horizon, the result is the same. For Congress to set a goal that the FAA should in general rely on competitive market forces is not to say that it must éngage in a calculation of the precise economic effects in every instance, especially whére those effects are quite remote from the factual question posed by the relevant statute, here simply “capacity.” We conclude, therefore, that the general “public interest” provisions of the Federal Aviation Act did not require the FAA to consider either the possibility that its decision would cause Northwest economic pain or the more remote prospect that its ruling would, in turn, adversely affect airline competition.

C. FAA’s Approval of Alternative Projects

Northwest next raises two challenges related to the FAA’s acceptance of Memphis’s alternative “noise compatibility project” as a basis for approving the Memphis PFC. Northwest first argues that the FAA’s policy of approving applications to impose PFCs for alternative uses violates the plain language of the PFC statute. Even if the “alternative use” policy is valid, however, Northwest argues that the FAA’s decision must be' set aside because Memphis disregarded its statutory obligation to consult with the airline regarding its alternative noise compatibility project before filing its application to impose a PFC. We consider these challenges in turn.

1. The FAA’s “Alternative Use” Approval Policy

The PFC statute requires that the FAA only grant “authority to impose a fee under [the PFC statute] to finance specific projects.” 49 U.S.C. § 1513(e)(2) (emphasis added). Northwest contends that the FAA’s policy of approving projects “in the alternative” violates this statutory command because it allows airport authorities to impose a PFC without first selecting a specific use for the funds. We disagree.

FAA regulations authorize airport agencies to “apply for the authority to impose PFCs in advance of ... an application to use PFC revenue,” 14 C.F.R. § 158.25(a) (1993) (emphasis added), provided that the airports’ applications include a “description of alternative uses of the PFC revenue to ensure that such revenue will be used only on eligible-projects in the event the proposed [primary] project is not [ultimately] approved,” id. § 158.25(b)(14)(ii). The selection among these approved projects is made at a later date — when the airport authorities apply for FAA’s permission to use the PFC revenues on one or more of these approved projects. See id. § 158.25(c)(2).

As Northwest points out, by requiring FAA to approve requests “to impose” a PFC only “to finance specific projects,” 49 U.S.C. app. § 1513(e)(2), Congress plainly intended to link the power to collect PFC revenues with the duty to spend these funds on particular projects. In this way, Congress ensured that PFCs would be imposed only to fund “eligible airport related projects.Id. § 1513(e)(2)(B). However, the statute does not speak to whether the FAA must identify a single “eligible airport related project” at the time it authorizes imposition of a PFC or whether it may approve a group of eligible projects and later decide which of these eligible projects will ultimately be funded.

In light of this statutory silence, we move on to the second step of the Chevron analysis and ask whether the FAA’s adoption of a two-step approval process “is based on a permissible construction” of the PFC statute. Chevron, 467 U.S. at 837, 104 S.Ct. at 2779. We conclude that it is.

Northwest’s objection to the FAA’s “in the alternative” approval process is that the policy will lead to “all kinds of administrative artífice” because airport authorities will petition to impose PFCs for backup projects that clearly meet the criteria for PFC eligibility, but which the airports have no real intent to pursue. Petitioner’s Reply Br. at 9. Northwest thus raises the specter of airports collecting PFC revenue now, only to spend it later on non-PFC eligible projects. Yet, we fail to see the danger.

FAA regulations require that airport authorities applying for permission to impose a PFC before seeking authority to use the PFC funds must provide the FAA with a description of alternative PFC-eligible uses for the funds in order “to ensure that [PFC] revenue will only be used on eligible projects.” 14 C.F.R. § 158.25(b)(14)(ii). Once the airports are ready to spend the monies they have collected, they must again obtain the FAA’s blessing of their proposed projects. See id. § 158.25(c)(2). The agency thus checks twice to ensure that PFC funds are spent only on “eligible airport related projects.” These regulatory safeguards lead us to conclude that the FAA’s two-step approval process is both “reasonable and consistent with the statute’s purpose.” Nuclear Info. Resource Serv., Resource Serv.969 F.2d at 1176. It is therefore entitled to deference.

2. Memphis’s Failure to Consult With the Airlines Regarding its Proposed Backup Project

The PFC statute requires that “[b]e-fore submission of an application under this paragraph, a public agency shall provide reasonable notice to, and an opportunity for consultation with, air carriers operating at the airport.” 49 U.S.C. app. § 1513(e)(ll)(C). This consultation must “provide air carriers [with a] description of projects [and] justifications for projects” to be funded through the imposition of PFCs. Id. Northwest argues that Memphis’s failure to consult with the airline regarding its alternative noise compatibility project before applying for permission to impose a PFC violated the express command of the PFC statute. We agree.

The FAA contends that Memphis’s failure to consult Northwest about its alternative project was not unlawful because the airline will be consulted regarding the noise compatibility project before Memphis seeks the FAA’s permission to spend its PFC funds. See 14 C.F.R. § 158.25(c)(2). But we cannot reconcile the agency’s post-hoc consultation mechanism with the plain language of the statute, which requires consultation “before submission of [a PFC] application.” 49 U.S.C. app. § 1513(e)(ll)(C)' (emphasis added).

We therefore hold that the FAA’s approval of the Memphis PFC violated the PFC statute insofar as it was based On a backup project for which no prior consultation with the airlines had occurred. Any attempt by Memphis to use its PFC funds to finance its noise compatibility project would therefore be unlawful. However, Memphis did consult with Northwest and the other airlines regarding its proposed primary projects before it applied to the FAA for permission to impose the PFC. Thus, with respect to the primary projects, no statutory violation occurred and Northwest can claim no harm. Memphis’s use of its PFC revenues to finance these primary projects would thus be unproblematic.

D. FAA’s Imposition of PFCs on Frequent Flyer Passengers

Finally, Northwest argues that by permitting Memphis to impose PFCs on passengers flying on no-fare “frequent flyer” tickets, the FAA violated the plain language of the PFC statute, which permits the FAA to authorize PFCs only “for each paying passenger of an air carrier enplaned at” the imposing airport. 49 U.S.C. app. § 1513(e)(1) (emphasis added). We do not decide this question, however, because Northwest failed properly to raise this issue before the agency and is thus barred by statute from presenting this claim in court.

The judicial review provision of the Federal Aviation Act states that “[n]o objection to an order of [the FAA] shall be considered by the court unless such objection shall have been urged before [FAA] or, if it was not so urged, unless there were reasonable grounds for failure to do so.” 49 U.S.C. § 1486(e). We have in the past construed this section strictly. See USAir, Inc. v. DOT, 969 F.2d 1256, 1259 (D.C.Cir.1992). See also Horizon Air Indus., Inc. v. DOT, 850 F.2d 775, 780 (D.C.Cir.1988).

Northwest nevertheless offers two reasons why we should reach the merits of its frequent flyer claim. First, Northwest argues that it did “urge” its frequent flyer objection before the FAA as required by § 1486(e). To make this claim, Northwest points to several communications between the airline and the FAA in which Northwest objected to the imposition of PFCs on frequent flyer customers. However, these letters were addressed to FAA officials in Washington, D.C., rather than to “the FAA Airports office identified in the Federal Register notice” as the place to submit public comments regarding the Memphis PFC application. 14 C.F.R. § 158.27(f)(2) (1993). These letters were thus directed to the wrong individuals to be considered in the context of the Memphis application. Furthermore, Northwest’s communications failed even to mention the pending PFC application to which they allegedly pertained. Instead, the letters merely requested that the FAA generally “reexamine [its] regulations with respect to their applicability to frequent flyer awards and provide the industry with a clear statement” of its policy.

Given the generality of Northwest’s submissions and the airline’s complete failure to comply with the procedural requirements set forth in the Federal Register for commenting on the Memphis PFC application, it is little wonder that its frequent flyer objections did not become a part of the FAA’s administra-five record and were not addressed in. the agency’s decision approving the Memphis PFC. Under these circumstances, we cannot say that Northwest “urged” its objections before the FAA within the meaning of § 1486(e).

Northwest next argues that we should address its frequent flyer argument, despite its failure to exhaust administrative remedies, because the FAA’s imposition of PFCs on frequent flyers clearly exceeds the authority granted the agency under 49 U.S.C. app. § 1513(e). Northwest relies on Washington Association for Television and Children [WATCH] v. FCC, 712 F.2d 677 (D.C.Cir.1983), which suggested in dicta that a party need not exhaust administrative remedies to challenge agency action that is “ ‘patently in excess of [the agency’s] authority.’ ” Id. at 682 (quoting Detroit Edison Co. v. NLRB, 440 U.S. 301, 312 n. 10, 99 S.Ct. 1123, 1129 n. 10, 59 L.Ed.2d 333 (1979) (dicta)).

However, several recent decisions of this Court have squarely rejected Northwest’s argument and have held that a party’s failure to raisean issue in the context of an administrative proceeding will not be excused merely because the litigant couches its claim in terms of the agency’s exceeding its statutorily-defined authority or “jurisdiction.”3 Mitchell v. Christopher, 996 F.2d 375 (D.C.Cir.1993); USAir, Inc. v. DOT, 969 F.2d 1256 (D.C.Cir.1992); Linemaster Switch Corp. v. EPA, 938 F.2d 1299 (D.C.Cir.1991); Natural Resources Defense Council v. Thomas, 805 F.2d 410 (D.C.Cir.1986). We have recognized that to adopt a contrary rule “permitting a petitioner to bring a statutory challenge to an agency’s action directly to this court “would infringe on agencies’ rightful role in statutory construction under the Chevron framework.’” USAir, 969 F.2d at 1260 (quoting Linemaster, 938 F.2d at 1308-09). We therefore hold that Northwest was required to raise its frequent flyer objection before the FAA in the context of the Memphis PFC proceeding and that its failure to do so precludes our resolution of that dispute.

III. CONCLUSION

The FAA’s decision approving Memphis’s primary projects and authorizing a $3.00 PFC at Memphis International Airport was based on a reasonable interpretation of the PFC statute. We therefore dismiss Northwest’s petition in large part. However, because Memphis’s failure to consult with Northwest and other airlines regarding its alternative noise compatibility project before applying for permission to impose the PFC violated the PFC statute, we hold that Memphis may not use its PFC revenues to finance this alternative project.

So ordered.

.

. The FAA derives its responsibility for administering the PFC statute from the Secretary of Transportation. 49 C.F.R. § 1.47 (1992).

49 C.F.R. § 1.47 (1992)..

. Petitioner's subsidiary argument that the FAA did not adequately consider whether a $1.00, $2.00, or $3.00 charge would be most appropriate fares no better. It depends on the necessity of the FAA considering the “negative impact" of the greater charge on the competitive factors asserted by Northwest. As we have already held that these are alternative factors to be considered by the FAA where it deems appropriate and not mandatory factors to be considered by the FAA in conjunction with the goal of the particular project, we reject the included challenge to the amount of the charge along with the greater argument challenging the charge as such.

It depends on the necessity of the FAA considering the “negative impact" of the greater charge on the competitive factors asserted by Northwest.As we have already held that these are alternative factors to be considered by the FAA where it deems appropriate and not mandatory factors to be considered by the FAA in conjunction with the goal of the particular project, we reject the included challenge to the amount of the charge along with the greater argument challenging the charge as such..

. While not explicitly relied upon by Northwest, we recognize that our decision in Railroad Yardmasters v. Harris, 721 F.2d 1332, 1338 (D.C.Cir.1983), did suggest that questions of agency “power or jurisdiction" may be raised on appeal “even if not initially asserted before the [agency]." However, subsequent decisions have limited the Yardmasters exception to the exhaustion requirement to "challenges that concern the very composition or ‘constitution’ of an agency.” Mitchell, 996 F.2d at 378.

Cir.1983), did suggest that questions of agency “power or jurisdiction" may be raised on appeal “even if not initially asserted before the [agency]."However, subsequent decisions have limited the Yardmasters exception to the exhaustion requirement to "challenges that concern the very composition or ‘constitution’ of an agency.” Mitchell, 996 F.2d at 378 .